Tafel Power

Ohio's Gas Queue Looks Empty Because Ohio Already Built Its Gas

For data centers weighing the Midwest: Ohio's queue shows almost no new gas, but it added 6.4 GW during the Utica boom and now pairs an existing fleet with cheap fuel and top-tier demand.

For hyperscalers · For infra funds · For developers · pjm · ohio · gas · utica · existing-fleet

Tafel Power · April 30, 2026 · 2 min read


Read Ohio through the interconnection queue and it looks like nothing is happening: about 0.9 GW of signed gas, which is essentially a single plant in late-stage construction with a queue in-service date of 2025, so it sits outside the 2026 to 2028 near-term window used to define deliverable gas. That reading misses the point, because Ohio already built its gas.

Ohio front-loaded its gas in the Utica boom

From 2015 to 2025, during the Utica shale buildout, Ohio added about 6.4 GW of new gas generation, so roughly 6.4 of its 16.4 GW of existing gas is post-2015. That is why the queue looks empty: the combined-cycle build that other markets are still trying to queue, Ohio largely completed last decade, next to the wellhead gas that fuels it. The queue-only lens, which works in a still-building merchant market, understates a market that already built.

The demand is here too

Ohio is not a quiet market on the demand side. Through the AEP zone and the Columbus data-center cluster, it is PJM's number two zone for forecast peak growth. So Ohio pairs three things that rarely sit together: installed dispatchable capacity, some of the cheapest gas in the country, and a top-tier data-center demand hub.

What this changes for the buyer

Hyperscaler energy leads. For a firm-gas campus, eastern and central Ohio deserve a closer look than the empty queue suggests. The relevant analysis is existing-fleet headroom, gas supply from the Utica, and behind-the-meter or existing-plant offtake, not a new queue position.

Infra funds. The Ohio opportunity is around installed and uprate-able capacity near cheap fuel and rising demand, not a merchant new-build queue thesis. Diligence the existing asset and its fuel logistics.

Methodology

The 0.9 GW signed-gas queue figure is reconciled from PJM's public New Services Queue (PlanningQueues feed) for Ohio: gas with an executed interconnection agreement, progressing, not already operating. Existing and recently built gas capacity, including the 2015 to 2025 additions and the roughly 16 GW total, are from EIA-860M (the federal monthly generator inventory), by state and operating year. Demand-growth ranking is from PJM's 2026 Load Forecast Report. These are Tafel Power's filtered estimates from public sources, not ISO-published categories. Figures reflect early-2026 snapshots and may have changed since.

All data compiled by Tafel Power from public sources. Framing informed by the firm's transaction advisory work in ERCOT and cross-ISO markets.


Share on LinkedIn

For discussions on ERCOT and cross-ISO power transactions, large-load diligence, or AI infrastructure power strategy: kris@tafelpower.com

More from Insights